215 Construction in Summerlin: How Phases Finish Through 2028

Clark County has two construction contracts running on the same stretch of the 215 Beltway, from Charleston Boulevard north to Lake Mead Boulevard. Together they cost $203.5 million, and both are scheduled to finish in 2028. The bigger one, the $130 million rebuild of the 215/Summerlin Parkway interchange, started in February 2025 and is due in spring 2028. The smaller one is a $73.5 million widening between Charleston and Far Hills Avenue. Las Vegas Paving started that job on June 1, 2026, and the county estimates it will be done in February 2028.

The 2028 end dates make the corridor sound like one long, even disruption. The county's own schedules show something different. The work finishes in stages, and they don't arrive in the order most drivers would expect. The first new piece of road could carry traffic by the end of this year, at the Summerlin Parkway end. The surface streets around Downtown Summerlin and Red Rock Casino Resort stay under construction through 2027. The freeway lanes beside them are the last to finish.

Two Contracts, One Strip of Freeway

The interchange project ends at Far Hills Avenue, and the widening project starts there, so the two jobs meet at Far Hills. North of that point, the interchange crews are rebuilding ramps and adding a flyover from the southbound 215 to eastbound Summerlin Parkway. The plan also includes five new vehicle bridges and three new bridges for the 215 Beltway pedestrian and bike trail. South of Far Hills, the widening reaches past the freeway into the streets that serve Downtown Summerlin. The county's project area covers Summerlin Centre Drive, Hughes Park Drive East and West, and Charleston Boulevard, along with both directions of the 215.

That split explains most of what follows. The northern job is mostly freeway work: ramps and bridges built away from local streets. The southern job runs into the surface streets that lead to the Downtown Summerlin shopping center and the Red Rock driveways.

What Is on the Ground This October

The county posts lane restrictions in short windows, so a sheet from two weeks ago may already be out of date. For the week of October 4, the interchange project has these 24/7 restrictions in place:

  • Southbound 215, Summerlin Parkway to Far Hills: two lanes and the shoulder closed.
  • 215 in both directions, Far Hills to Lake Mead: one lane and the shoulder closed, with a temporary traffic shift.
  • Westbound Summerlin Parkway, Anasazi Drive to the southbound 215 on-ramp: one lane open.
  • Far Hills northbound on-ramp: access to the northbound 215 is detoured.
  • The Beltway trail between Far Hills and Summerlin Parkway: detoured.

The county's look-ahead for the week of October 11 keeps the Far Hills detour to the northbound 215 in place.

On the Charleston-to-Far Hills side, the notice for September 27 through October 10 closes Red Rock Casino's north driveway. The south driveway stays open, and Hughes Park Drive East is closed to the north driveway. During the same window, Summerlin Centre Drive is down to one open lane in each direction with a dedicated left-turn lane at Hughes Park, and both halves of Hughes Park Drive are down to one lane plus a left-turn lane. The freeway itself keeps three lanes open northbound from Sahara to Far Hills and three lanes open southbound from Far Hills to Charleston during that period.

The driveway notice ends the day after the 30th Summerlin Festival of Arts opens. The festival runs October 9 through 11 on The Lawn, from 9 a.m. to 4 p.m. The Parade of Mischief steps off Fridays and Saturdays at 6 p.m. along Park Centre Drive through October 24. The county says Red Rock access will be maintained unless a message board says otherwise. It also says traffic on Summerlin Centre Drive and Hughes Park Drive East may be reduced to as little as one lane in each direction, plus a turn lane at signalized intersections.

The First Finished Piece Is at the Parkway

The interchange project is further along than most of the orange barrels suggest. As of the end of August, about 58 percent of the work had been billed, slightly ahead of the expected pace for a 1,102-day project, according to project manager Dan Erickson. Crews have finished all but one of the five vehicle bridges, and the last one is set for completion by the end of the year. Erickson told the Las Vegas Review-Journal that the next stretch of work should not require major lane closures:

"This project shouldn't have any closures coming up anytime soon. The major portion of the work is the walls and bridge, and that is all outside of traffic."

He named the next milestone as traffic moving onto the new ramp from westbound Summerlin Parkway to the northbound 215. That ramp will run under the new pedestrian bridge on the northeast corner. Erickson said "That should happen maybe November or December. Cars will be on the ultimate alignment." That makes it the first permanent piece of the new interchange to carry traffic. It comes from a September forecast, not a posted traffic notice, so the date is still an estimate.

The congestion Erickson does see comes from the grade itself, not from a lane closure. "Backups I see are where you're heading south (on 215) and climbing that hill, concrete trucks or big trucks climbing the hill from Cheyenne towards Lake Mead," he said, adding that those trucks can only climb at about 10 mph.

The Downtown Summerlin Side Runs on a Longer Clock

On the Charleston-to-Far Hills job, the work moves from the surface streets onto the freeway over time. The county's phase chart lists five phases:

  1. Hughes Park Drive East, June 2026 to December 2026. A temporary shoofly, storm drain, the braided bridge and overhead signage.
  2. Charleston Boulevard overpass, August 2026 to March 2027. Traffic signal modifications.
  3. Northbound 215, August 2026 to August 2027. Storm drain, ITS, concrete widening, striping and signage.
  4. Hughes Park Drive West, September 2026 to June 2027. Storm drain, ITS, roadway restoration and signage.
  5. Southbound 215, April 2027 to January 2028. The same widening package as the northbound side.

The county labels the chart "for reference only" and says phasing and scope may change. The documents also disagree on a few details. In March, the Review-Journal reported a 540-day work schedule, while the phase chart lists 600 calendar days. The listed work hours vary from sheet to sheet. The construction notice gives weekdays from 7 a.m. to 4 p.m. with periodic overnight shifts from 9 p.m. to 5 a.m. The phase chart lists nightly work from Sunday night through early Friday. Every version includes overnight work.

Read in order, the chart shows the surface streets around Downtown Summerlin in active work through mid-2027 on the Hughes Park West phase. Work on the southbound freeway lanes doesn't start until April 2027 and runs to January 2028. The holiday season falls inside the Hughes Park East phase. As of September 25, Summerlin's events page did not yet list 2026 dates for the tree lighting, holiday parade or Rock Rink, so it isn't yet clear how those events will line up with the work.

What the Finished Road Does Differently

The widening adds one lane in each direction of the 215 between Charleston and Far Hills. It also adds a braided ramp from the northbound 215 to Charleston that crosses over Hughes Park Drive East. Clark County principal civil engineer Rahel Shibeshi said the new ramps will let drivers on Summerlin Centre Drive get on the freeway directly without going through Charleston. Drivers leaving the 215 will be able to reach Charleston directly. At the Parkway, the finished interchange adds the southbound flyover to Summerlin Parkway and widens the Summerlin Parkway bridge over the 215.

The trail is the last piece. The new pedestrian and bike bridges are already built, but the paths leading to them won't open until close to the end of the project. "There's still a lot of dirt to move," Erickson said. Until then, the Far Hills-to-Summerlin Parkway section of the trail stays detoured. That means the trail bridges are already finished but will be among the last pieces to open. The county posts each week's restrictions on its CC-215 Charleston to Far Hills project page. It's the most reliable place to check before a Saturday at Downtown Summerlin or a dinner reservation at Red Rock.

A project schedule that runs to 2028 affects everyday decisions in Summerlin, including when to schedule a showing, a move-in truck or a weekend open house around a detour. If you're planning around any of it, Avi Dan-Goor and our team can map those dates for your address. Request a Private Consultation.